From the meeting · Planning Commission, · 1:08
Why does the host district's fee share last only three years?
Staff's proposed data center standards set aside 35% of the fees for the host council district for three years; during commission deliberation, the chair asks how that compares with how long a data center operates.
the chair, a speaker and city staff
Automatic captions
Speech-to-text from the recording, unchecked.
the chair What's the lifespan of a data center?
a speaker Twenty to thirty years.
the chair Okay.
the chair So they live with the harm and impact for twenty, thirty years, but they only get 35% of the fees for three.
city staff I think an important point is that they're still eligible to...
city staff Even though we would make some of those dollars available citywide if there was an uptake there, people in those neighborhoods could still apply.
city staff They're not excluded.
the chair Yeah.
the chair I think we could be more careful and deliberate about that.
the chair Think if you can think of three years, you can think of the lifespan of the project.
the chair I don't understand why you picked three years.
a speaker There are limitations with regards to fees that they have to be committed within a certain time period, typically within five years.
a speaker So that's what we said.
a speaker What we we that's the three year criteria.
a speaker Because if they're not committed within those three years, then we want them to have the flexibility for the next two to be able to commit those citywide.
a speaker So that was intentional to make sure that we're following the law.
Where it's from
- Citywide standards and permit rules for data centers and other large energy projects Item 5a: what happened
- The episode: San Jose pauses data center approvals; commission backs new rules
- The full recording from here